Problem with the Actual Work from PWA

V

Victor

I've got some strange behaviors with the actual work inserted from pwa.
We use tasks fixed work and often our planned tasks are split in many parts
during execution phase.
We have 2 king of behaviors
1- Some times the actual work in the Resource Usage View changes values and
some decimal appear (8.88 or 7.12).
2- Normally Saturday is NoWorking day but some times we work also on
Saturday.When we import the actual work from PWA on Monday (after a Week
with Saturday working day) Project inserts some Actual Work hours on Monday.
This is very strange because the Team Member have not yet to create the
TimeSheet for next week.

Thank you for your help!

Victor
 
M

Mike Glen

Hi Victor ,

Try posting on the microsoft.public.project.server newsgroup (forum).
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
V

Victor

Thanks Mike
I inserted a new post in microsoft.public.project.server newsgroup (forum).
Victor
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top