Hello all,

I've learned that in order to properly delete tasks from
an already published plan, it is easiest to export the
plan to an exisitng mpp, delete the project from the
server, and re-import the plan into the server via tools-
enterprise option-> import projects to enterprise.

Each time that I perform this operation, I manage to
improperly get tables and view such as entry and usage
into the enterprise global. I then have to remove then
before I can proceed with the newly imported project.

What am I doing incorrectly here? Am I exporting or
importing incorrectly? Do I have a more basic problem
with my enterprise global?

As always, any assistance is really appreaciated.

Thanks,

Damian
 
G

Gary Chefetz [MVP]

Damian:

To answer the other part of your question, it sounds like you have the
enterprise global open while you're importing project plans. That would
explain the enterprise global pollution.

--
Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top