TerryW
I have created a project that has sub-tasks durations that roll up to
summary-tasks. The summary-tasks durations that roll up to a project total.
Everything is linked and is all totaling up correctly. I have resources that
I want to apply to tasks but everytime I do that the total duration time of
the project goes up as well as the completion date goes farther and farther
out as I add resources. I expected it to do the opposite and get shorter. The
tasks are all fixed work tasks. Any suggestions as to what i am doing wrong
or how I can get this to work right?
summary-tasks. The summary-tasks durations that roll up to a project total.
Everything is linked and is all totaling up correctly. I have resources that
I want to apply to tasks but everytime I do that the total duration time of
the project goes up as well as the completion date goes farther and farther
out as I add resources. I expected it to do the opposite and get shorter. The
tasks are all fixed work tasks. Any suggestions as to what i am doing wrong
or how I can get this to work right?