B
Bobby
I recently upgraded from Project 2003 to Project 2007 (beta).
I'm having a problem with task durations. When I try to enter "3 weeks" into
the duration column it automatically changes to "2.98 weeks" and screws up
the total number of days for the task summary and other project totals.
Why is this? Why doesn't it just accept my 3 week duration? Why is it
changing to 2.98 weeks?
Cheers.
(PS Project 07 looks pretty much like Project 03 so I might just go back to
the earlier version. Is there any much changed?)
Bobby
I'm having a problem with task durations. When I try to enter "3 weeks" into
the duration column it automatically changes to "2.98 weeks" and screws up
the total number of days for the task summary and other project totals.
Why is this? Why doesn't it just accept my 3 week duration? Why is it
changing to 2.98 weeks?
Cheers.
(PS Project 07 looks pretty much like Project 03 so I might just go back to
the earlier version. Is there any much changed?)
Bobby