C
Catfish Hunter
Does anyone know how to make the progress bar show up w/o giving % complete?
Would like to have it move with the current date.
Would like to have it move with the current date.
JulieS said:Hi Catfish,
I assume you are referring to the progress bars drawn on the Gantt
bars not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar Styles,
but you can create a custom Finish field (for example Finish10), set
the formula for Finish10 to [Current Date] and then use Finish10 as
the "To" in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
Catfish Hunter said:Does anyone know how to make the progress bar show up w/o giving %
complete?
Would like to have it move with the current date.
JulieS said:Hi Catfish,
I assume you are referring to the progress bars drawn on the Gantt bars
not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar Styles,
but you can create a custom Finish field (for example Finish10), set the
formula for Finish10 to [Current Date] and then use Finish10 as the "To"
in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
Catfish Hunter said:Does anyone know how to make the progress bar show up w/o giving %
complete?
Would like to have it move with the current date.
Catfish Hunter said:Julie, Can not find Current Date as an option under costumize.
JulieS said:Hi Catfish,
I assume you are referring to the progress bars drawn on the Gantt
bars
not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar
Styles,
but you can create a custom Finish field (for example Finish10), set
the
formula for Finish10 to [Current Date] and then use Finish10 as the
"To"
in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
Catfish Hunter said:Does anyone know how to make the progress bar show up w/o giving %
complete?
Would like to have it move with the current date.
JulieS said:Hi Catfish,
Insert the custom field (Finish 10 for example) in a table. With the
custom field selected, right click to show the shortcut menu and choose
Customize Field to show the Customize Fields dialog box. Click on the
Formula... button. In the Formula dialog box, click the Field drop
down, select Project > Date > Current date. That will insert [Current
Date] in the Formula dialog box. You may also just type [Current Date]
in the Formula dialog box.
Hope this helps.
Julie
Catfish Hunter said:Julie, Can not find Current Date as an option under costumize.
JulieS said:Hi Catfish,
I assume you are referring to the progress bars drawn on the Gantt
bars
not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar
Styles,
but you can create a custom Finish field (for example Finish10), set
the
formula for Finish10 to [Current Date] and then use Finish10 as the
"To"
in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
message Does anyone know how to make the progress bar show up w/o giving %
complete?
Would like to have it move with the current date.
Catfish Hunter said:Julie this woks but...
As the current date goes past when the task actually completed the
progress
bar continues to move with the current date. Any ideas on how to make
it stop
when the task is complete?
JulieS said:Hi Catfish,
Insert the custom field (Finish 10 for example) in a table. With the
custom field selected, right click to show the shortcut menu and
choose
Customize Field to show the Customize Fields dialog box. Click on the
Formula... button. In the Formula dialog box, click the Field drop
down, select Project > Date > Current date. That will insert
[Current
Date] in the Formula dialog box. You may also just type [Current
Date]
in the Formula dialog box.
Hope this helps.
Julie
Catfish Hunter said:Julie, Can not find Current Date as an option under costumize.
:
Hi Catfish,
I assume you are referring to the progress bars drawn on the Gantt
bars
not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar
Styles,
but you can create a custom Finish field (for example Finish10),
set
the
formula for Finish10 to [Current Date] and then use Finish10 as
the
"To"
in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
in
message Does anyone know how to make the progress bar show up w/o giving
%
complete?
Would like to have it move with the current date.
JulieS said:Hi Catfish,
I don't understand what you are trying to accomplish but the following
formula will set the value in Finish10 to Actual Finish if the task is
100%, if not it sets it to the current date:
IIf([% Complete]<1,[Current Date],[Actual Finish])
Perhaps if you could explain what you are trying to do I can be of more
assistance.
Julie
Catfish Hunter said:Julie this woks but...
As the current date goes past when the task actually completed the
progress
bar continues to move with the current date. Any ideas on how to make
it stop
when the task is complete?
JulieS said:Hi Catfish,
Insert the custom field (Finish 10 for example) in a table. With the
custom field selected, right click to show the shortcut menu and
choose
Customize Field to show the Customize Fields dialog box. Click on the
Formula... button. In the Formula dialog box, click the Field drop
down, select Project > Date > Current date. That will insert
[Current
Date] in the Formula dialog box. You may also just type [Current
Date]
in the Formula dialog box.
Hope this helps.
Julie
message Julie, Can not find Current Date as an option under costumize.
:
Hi Catfish,
I assume you are referring to the progress bars drawn on the Gantt
bars
not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar
Styles,
but you can create a custom Finish field (for example Finish10),
set
the
formula for Finish10 to [Current Date] and then use Finish10 as
the
"To"
in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
in
message Does anyone know how to make the progress bar show up w/o giving
%
complete?
Would like to have it move with the current date.
Catfish Hunter said:At this job site I can not get % complete. The client will not give
this to me.
I still need to see the progress bar. I need to to stop when the task
is
complete. The last formula you sent works for most cases and I can
live with
that. Unless you have a better idea.
JulieS said:Hi Catfish,
I don't understand what you are trying to accomplish but the
following
formula will set the value in Finish10 to Actual Finish if the task
is
100%, if not it sets it to the current date:
IIf([% Complete]<1,[Current Date],[Actual Finish])
Perhaps if you could explain what you are trying to do I can be of
more
assistance.
Julie
Catfish Hunter said:Julie this woks but...
As the current date goes past when the task actually completed the
progress
bar continues to move with the current date. Any ideas on how to
make
it stop
when the task is complete?
:
Hi Catfish,
Insert the custom field (Finish 10 for example) in a table. With
the
custom field selected, right click to show the shortcut menu and
choose
Customize Field to show the Customize Fields dialog box. Click on
the
Formula... button. In the Formula dialog box, click the Field
drop
down, select Project > Date > Current date. That will insert
[Current
Date] in the Formula dialog box. You may also just type [Current
Date]
in the Formula dialog box.
Hope this helps.
Julie
in
message Julie, Can not find Current Date as an option under costumize.
:
Hi Catfish,
I assume you are referring to the progress bars drawn on the
Gantt
bars
not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar
Styles,
but you can create a custom Finish field (for example
Finish10),
set
the
formula for Finish10 to [Current Date] and then use Finish10 as
the
"To"
in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
"Catfish Hunter" <[email protected]>
wrote
in
message
Does anyone know how to make the progress bar show up w/o
giving
%
complete?
Would like to have it move with the current date.
JulieS said:Hi Catfish,
I'm glad the formula works. It sounds as if you just want the "visual"
of the progress bar but can't really get accurate tracking data? Have
you thought about using the Update as Scheduled command on the Tracking
toolbar? That will mark tasks as complete through the Status Date or
Current Date.
Julie
Catfish Hunter said:At this job site I can not get % complete. The client will not give
this to me.
I still need to see the progress bar. I need to to stop when the task
is
complete. The last formula you sent works for most cases and I can
live with
that. Unless you have a better idea.
JulieS said:Hi Catfish,
I don't understand what you are trying to accomplish but the
following
formula will set the value in Finish10 to Actual Finish if the task
is
100%, if not it sets it to the current date:
IIf([% Complete]<1,[Current Date],[Actual Finish])
Perhaps if you could explain what you are trying to do I can be of
more
assistance.
Julie
message Julie this woks but...
As the current date goes past when the task actually completed the
progress
bar continues to move with the current date. Any ideas on how to
make
it stop
when the task is complete?
:
Hi Catfish,
Insert the custom field (Finish 10 for example) in a table. With
the
custom field selected, right click to show the shortcut menu and
choose
Customize Field to show the Customize Fields dialog box. Click on
the
Formula... button. In the Formula dialog box, click the Field
drop
down, select Project > Date > Current date. That will insert
[Current
Date] in the Formula dialog box. You may also just type [Current
Date]
in the Formula dialog box.
Hope this helps.
Julie
in
message Julie, Can not find Current Date as an option under costumize.
:
Hi Catfish,
I assume you are referring to the progress bars drawn on the
Gantt
bars
not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar
Styles,
but you can create a custom Finish field (for example
Finish10),
set
the
formula for Finish10 to [Current Date] and then use Finish10 as
the
"To"
in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
"Catfish Hunter" <[email protected]>
wrote
in
message
Does anyone know how to make the progress bar show up w/o
giving
%
complete?
Would like to have it move with the current date.
Catfish Hunter said:At this job site I can not get % complete. The client will not give this
to me.
I still need to see the progress bar. I need to to stop when the task is
complete. The last formula you sent works for most cases and I can live
with
that. Unless you have a better idea.
JulieS said:Hi Catfish,
I don't understand what you are trying to accomplish but the following
formula will set the value in Finish10 to Actual Finish if the task is
100%, if not it sets it to the current date:
IIf([% Complete]<1,[Current Date],[Actual Finish])
Perhaps if you could explain what you are trying to do I can be of more
assistance.
Julie
Catfish Hunter said:Julie this woks but...
As the current date goes past when the task actually completed the
progress
bar continues to move with the current date. Any ideas on how to make
it stop
when the task is complete?
:
Hi Catfish,
Insert the custom field (Finish 10 for example) in a table. With the
custom field selected, right click to show the shortcut menu and
choose
Customize Field to show the Customize Fields dialog box. Click on the
Formula... button. In the Formula dialog box, click the Field drop
down, select Project > Date > Current date. That will insert
[Current
Date] in the Formula dialog box. You may also just type [Current
Date]
in the Formula dialog box.
Hope this helps.
Julie
message Julie, Can not find Current Date as an option under costumize.
:
Hi Catfish,
I assume you are referring to the progress bars drawn on the Gantt
bars
not progress the progress line.
The [Current Date] does not appear as a choice in Format > Bar
Styles,
but you can create a custom Finish field (for example Finish10),
set
the
formula for Finish10 to [Current Date] and then use Finish10 as
the
"To"
in the Bar Styles option.
I hope this helps. Let us know how you get along.
Julie
in
message Does anyone know how to make the progress bar show up w/o giving
%
complete?
Would like to have it move with the current date.
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.