A
Andrei
Hi,
I use Grouping in my project rather extensively. Unfortunately, I still can
not figure out if I can display progress on "Group by" summary tasks the same
way it is displayed in "normal" summary tasks on a Gantt chart.
i used "actual start - complete through" , "actual start - summary
progress" and other combinations on "format bar styles" menu, but managed
only to show the progress formatted bar for the summary bars, when entered
"actual start - finish" or "start - finish" in "from" - "to" fields. So I
know I format the right bar, but not in hte right way, so I can display the
progress correctly, as it just goes all the way from start to finish,
parallel to the task itself.
Is there a possibility to show the progress on "Group by" Summary tasks at
all?
And if yes, how on earth
)
If anyone experienced the same problem and have a solution, please help.
Andrei
I use Grouping in my project rather extensively. Unfortunately, I still can
not figure out if I can display progress on "Group by" summary tasks the same
way it is displayed in "normal" summary tasks on a Gantt chart.
i used "actual start - complete through" , "actual start - summary
progress" and other combinations on "format bar styles" menu, but managed
only to show the progress formatted bar for the summary bars, when entered
"actual start - finish" or "start - finish" in "from" - "to" fields. So I
know I format the right bar, but not in hte right way, so I can display the
progress correctly, as it just goes all the way from start to finish,
parallel to the task itself.
Is there a possibility to show the progress on "Group by" Summary tasks at
all?
And if yes, how on earth
If anyone experienced the same problem and have a solution, please help.
Andrei