W
Wajih
I made a Plan and that Time i assigned 200 Hours and 3 Resources on a Task.
But at the time of Project Execution the Scenario is different all i need is
the 1 Resouce with 100 Hours for the same duration. The Plan is Baseline. If
I remove any Resource then the Total time of my Project are being changed. i
Dont want that. But if i mark that task to 100% then it means that 200 hours
worked performed on that task . whereas in actual it was 100 hours. How can i
handle this situation
But at the time of Project Execution the Scenario is different all i need is
the 1 Resouce with 100 Hours for the same duration. The Plan is Baseline. If
I remove any Resource then the Total time of my Project are being changed. i
Dont want that. But if i mark that task to 100% then it means that 200 hours
worked performed on that task . whereas in actual it was 100 hours. How can i
handle this situation