P
pm9000
Hi all,
I have marked some tasks as 100% complete, but when I try Tools,
Tracking, Update Project - I get "did not reschedule some tasks"
because of constraints.
I'm a bit confused by this "Update Project". Is it really necessary
to run this. Can't I just do a level on the project?
Many thanks,
Mark
I have marked some tasks as 100% complete, but when I try Tools,
Tracking, Update Project - I get "did not reschedule some tasks"
because of constraints.
I'm a bit confused by this "Update Project". Is it really necessary
to run this. Can't I just do a level on the project?
Many thanks,
Mark