K
kschuster
Newbie here.
My typical project may span 6 months. I may budget 20 hrs to complete
The actual time to complete may only be 5 hrs.
How do I setup Project to show the variance between budget and actual?
How do I mark a task as complete? I seems changing the %Complet
forces WORK and ACTUAL WORK to the same values - which defeats m
objective.
I was thinking Baselines would accomplish this - but my project is i
constant flux in terms of tasks, thus changing the baseline t
accomidate the new tasks would be required (I think - agian newbi
here)
Can someone lend some guidence
Thank
My typical project may span 6 months. I may budget 20 hrs to complete
The actual time to complete may only be 5 hrs.
How do I setup Project to show the variance between budget and actual?
How do I mark a task as complete? I seems changing the %Complet
forces WORK and ACTUAL WORK to the same values - which defeats m
objective.
I was thinking Baselines would accomplish this - but my project is i
constant flux in terms of tasks, thus changing the baseline t
accomidate the new tasks would be required (I think - agian newbi
here)
Can someone lend some guidence
Thank