O
One too many
This is a repeatable bug across my project.
I have a project which I am working backwards from a deadline, so the tasks
are all set to "As late as possible". The tasks are put at one point in
time, but the task roll ups dates seem to default to now.
Example:
- Task Summary 40 days 1/4/2005 10/5/2005
Task item1 20 days 1/8/2010 20/8/2010
Task item2 20 days 21/8/2010 10/9/2010
(note the summary dates do not match the task item dates)
Any ideas if there is a fix for this problem?
Thanks
R
I have a project which I am working backwards from a deadline, so the tasks
are all set to "As late as possible". The tasks are put at one point in
time, but the task roll ups dates seem to default to now.
Example:
- Task Summary 40 days 1/4/2005 10/5/2005
Task item1 20 days 1/8/2010 20/8/2010
Task item2 20 days 21/8/2010 10/9/2010
(note the summary dates do not match the task item dates)
Any ideas if there is a fix for this problem?
Thanks
R