Hello,
I have a project that needs to be scheduled in Hours and Minutes over the
course of 1 to 2 days.
Here is what I have done so far:
1) Tools\Change Working Time - To start at 4:00 am and go until 10:00 PM
2) Tools\Options\Calendar - Changed Default Start Time to 4:00 AM and
Default End Time to 10:00 PM
3) Tools\Options\Schedule - Duration is entered in Minutes
However, no matter what I do, I can never seem to start any tasks at 4:00 am.
Am I missing something? Is this too much for Project 2000?
Thanks in advance.
Jeff
I have a project that needs to be scheduled in Hours and Minutes over the
course of 1 to 2 days.
Here is what I have done so far:
1) Tools\Change Working Time - To start at 4:00 am and go until 10:00 PM
2) Tools\Options\Calendar - Changed Default Start Time to 4:00 AM and
Default End Time to 10:00 PM
3) Tools\Options\Schedule - Duration is entered in Minutes
However, no matter what I do, I can never seem to start any tasks at 4:00 am.
Am I missing something? Is this too much for Project 2000?
Thanks in advance.
Jeff