Project 2002/3 Filtering Question (2nd attempt)

T

Tel

Hi,

Sorry, I am posting this again as I never got a reply to my previous
posting.

I have a project where the tasks have a number of different resources
assigned to them.

By using filters, I am trying to get the resource usage view to show only
the resource totals for tasks against the filter I have applied. The filter
lists out the selected tasks okay, but the totals against the resource
contain the total for all the tasks (i.e work, %cmpl, etc) assigned to the
resource throughout the plan and
ignores the filter.

Does anyone know how I can show the resource totals for only those tasks I
have chosen?

Project MPV assistants - Do you not know the answer to this question? If so,
can you please reply and I'll stop bothering this newsgroup.


Thanks

Paul
 
M

Mike Glen

Hi Tel,

I don't think what you want is possible in Project. However I'm sure that
it can be extracted using vba code. Try posting on the developer newsgroup.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://www.mvps.org/project/.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top