Project 2002/3 Filtering Question

T

Tel

Hi,

Sorry, I am posting this again as I never got a reply to my previous
posting.

I have a project where the tasks have a number of different resources
assigned to them.

By using filters, I am trying to get the resource usage view to show only
the resource totals for tasks against the filter I have applied. The filter
lists out the selected tasks okay, but the totals against the resource
contain the total for all the tasks (i.e work, %cmpl, etc) assigned to the
resource throughout the plan and
ignores the filter.

Does anyone know how I can show the resource totals for only those tasks I
have chosen?

Project MPV assistants - Do you not know the answer to this question? If so,
can you please reply and I'll stop bothering this newsgroup.


Thanks

Paul
 
S

Steve House [MVP]

AFAIK you can't do what you want in the usage view. OTOH, you should be
able to do it in to hard copy from the reports menu and creating a custom
report.
 

Ask a Question