R
Rag742
I have tasks that has 4days duration. I know the resource of the
project manager(PM) is 12 labor hours. Is there some way I can enter
the PM labor hour as 12 . At present if i enter 12 hours it changes
the duration and the resource unit also changes. I don't care about
the resource unit all i want the 4days duration and 12 hours.
Thanks Rag742
project manager(PM) is 12 labor hours. Is there some way I can enter
the PM labor hour as 12 . At present if i enter 12 hours it changes
the duration and the resource unit also changes. I don't care about
the resource unit all i want the 4days duration and 12 hours.
Thanks Rag742