Steve,
I ran on to your reply while exploring how resolve our situation. I
read
it
an understand it; however, here is situation.
First, we use MS Project primarily as a schedule tracking tool, that
is,
are
we on schedule per the Start/Finish dates and %Complete estimates.
Second,
we
want to know when a resource is overallocated.
For the schedule, we find it may only take a resource 1 day to complete
the
task; however, with their other demands, etc. it takes the resource 5
days
to
expend that 1 day. Therefore, if we let the duration be 1 day, like MS
Project wants to do via it three Task types Fixed Duration, Fixed Units
and
Fixed Work, then MS Project will understate the Finish date as to when
we
will likely receive the task deliverable.
For the hours, when duration is set to 5 days, then, based on a 4-day,
10
hours/day schedule, MS Project will set the Work Hours to 40, not the
10
hours the task is likely to take.
I don't see how to set a default to allow us to enter a duration of 5
days
and work hours of 10 hours. We can force it for each task individually
by
setting the task to Fixed Duration, not Effort Driven and overriding by
using
the drop box that appears in the work hours column.
If you have a better way, please let me know.
Thank you,
Michael
:
Work = Duration * Units ... always. Fixed Duration says the time
frame
never changes. But does that make sense? If you are going to paint a
room
and it'll take one painter a week to do it because he's also doing
something
else at the same time and can only work on it 50%, isn't it logical
that
if
you can free him up from that other assignment so he can work on the
room
100%, it should finish in half the time? But you're saying you don't
want
Project to calculate it like that. Non-effort driven says that if we
have
1 painter on the room taking a week and can manage to find another
painter
to work with him, when we put the second painter on the job it should
still
be scheduled to take a week. Is that logical? Yet that's exactly the
way
your post says you want Project to schedule it - you're allowing a
week
for
the painting and it'll be scheduled for that regardless of whether we
put
1
painter, 2 painters, or a dozen of them on the job.
Why are you trying to schedule like this? It seems like you have a
preconceived notion of what the schedule 'ought' to be and are trying
to
make the project plan fit into that framework rather than giving
Project
the
parameters of the project and lettting it tell YOU the dates you
should
plan
to do the tasks in order to achieve the results on-time and within
budget.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
I always have put my project at "non effort driven" and "fixed
duration"
to
set up a new schedule. When I converted from MP2003 to MP2007; my
dates
jumped around. IS THERE ANYWAY POSSIBLE TO KEEP THE WORK HOURS
CONSTANT
ON
A
FIXED DURATION SCHEDULE? I know I could set up "fixed work" but then
if
the
dates change, the work would change to compensate. I didn't have
this
problem
is earlier editions of project.