The decision has been made by the organization for which I am working to have
a project administrator control update of project plans. We are not goiong to
be using ProjectServer although it was recommended. We are using MS Project
2003 professional. There will be at least 2 project managers updating the
project plans. In some cases these are the same project plans. We have
recommended a common resource pool and that appears to be accepted. Do you
have any suggestions on how the project administration might work? How would
you suggest the administrator update the plans? How would you suggest the
project managers provide the updates? Any advice on reporting the updates to
the executive? I know this is not the recommended route nor "best practice"
but we are contrained by executive decision.
 