Brian
I have the working days in my calendar set to Monday through Friday. However, when I have tasks cross a weekend (i.e. a 10 day task), the weekends days are included in the task as working days. Any suggestions how I can keep my weekends as non-working time
Thanks
Brian
Thanks
Brian