Project Calendar

B

Brian

I have the working days in my calendar set to Monday through Friday. However, when I have tasks cross a weekend (i.e. a 10 day task), the weekends days are included in the task as working days. Any suggestions how I can keep my weekends as non-working time

Thanks
Brian
 
G

Gérard Ducouret

Hello Brian,
The tasks bars cross the weed-end but they don't use it. Count all the
working days. MS Project durations are specified in working days by default.
You can set Ms Project to dsiplay the non-working time in front of the tasks
bars :
Format / Timescale... / Non working time / Draw : In front off...

Hope this helps,

Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris

Brian said:
I have the working days in my calendar set to Monday through Friday.
However, when I have tasks cross a weekend (i.e. a 10 day task), the
weekends days are included in the task as working days. Any suggestions how
I can keep my weekends as non-working time?
 