D
dm0502
I have a custom report based on the Top-level Task report, which displays all
tasks, with predecessor and successor task descriptions.
This report is being used on a Master Project that has 3 inserted projects,
with links between the 3 projects. Is there a way for the task description,
predecessors and successors to show the Project ID that the task belongs to?
For example:
Project A has a Task 1 as does Project B and Project C. Project A task 1 is
linked to Project C task 4. The report displays:
Task 1
Predecessor: Task 4
Task 1
Task 1
Task 4
Successor: Task 1
Is there a way to display on the report:
Project A:Task 1
Predecessor: Project C:Task 4
Project B:Task 1
Project C:Task 1
Project C:Task 4
Successor: Project A:Task 1
This is what is displayed on the task info predecessors tab, but not on the
report. I’m not sure if there is an option for this.
TIA
tasks, with predecessor and successor task descriptions.
This report is being used on a Master Project that has 3 inserted projects,
with links between the 3 projects. Is there a way for the task description,
predecessors and successors to show the Project ID that the task belongs to?
For example:
Project A has a Task 1 as does Project B and Project C. Project A task 1 is
linked to Project C task 4. The report displays:
Task 1
Predecessor: Task 4
Task 1
Task 1
Task 4
Successor: Task 1
Is there a way to display on the report:
Project A:Task 1
Predecessor: Project C:Task 4
Project B:Task 1
Project C:Task 1
Project C:Task 4
Successor: Project A:Task 1
This is what is displayed on the task info predecessors tab, but not on the
report. I’m not sure if there is an option for this.
TIA