Project Interaction

J

JimS

I have about a dozen project segments, each running 200-3,000 tasks that are
parts of the same project. They are managed by different managers, and are
somewhat interdependent, but mostly dependent on another project managed in
Primavera P6 offsite.

I need to pull these project schedules together, particularly to identify
their interdependencies, but also to share resources. 90% of the resources
are dedicated to a project segment, but the other 10% are cross-allocated.
Examples:

An engineer is responsible for training and execution of commissioning, but
is also responsible to review and approve others' work from other teams.

I know the absolute best way to handle this is MS Project Server (assuming I
don't want to use Primavera....) I don't think I'm going to have that option,
so I think there are two other options:

1. All the subprojects stored in a single place, with version control and
(hopefully) checkout capability. What I don't know is if this provides for
shared resources and the ability to reschedule the entire project at once. It
does allow each manager to status his/her own project segments without
onerous controls.

2. A single project with subproject heirarchy. This seems onerous in terms
of access by users for progressing, etc. It also has risks that the whole
project could be ruined by a single mistake, however well-intentioned.

If I opt for option 1, and create a "main" project that could, for example,
contain "links" back to the P6 "master" schedule, and contain all the
resources, shared or otherwise, with all the "subprojects" linking back to
it, that would seem ideal. Is that practical? appropriate?

Resources?
 
V

vanita

Hi Jim

Ideally the whole project should be on one software, either use MSP or P6,
because there is always some problem of data format etc. while
importing/exporting data between the two software e.g I have come across
problem of importing customised Calendars from P6 to MSP.

As per my experience Option 2 suits your requiremnet well. Compliment it
with taking frequent data backups and it shoudl not be an issue.

I hope it helps
Vanita
 
H

HankB

Jim

You can accomplish option #1 using "resource pools". This will let you
share resources among projects and sycnch your tasks around the staff you
have available.

Hank
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top