Hi Lynn,
I'm not sure I understand. The duration of the task should be
calculated by the linked start and end dates.
I assume you created the hammock task as outlined in the FAQ? You'll
need to assign your resource or resources at 15% assignment units to the
task to show the resource allocation and work.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project