Project Pro and PWA Project view out of sync

B

bauer172uw

We have a situation where our Project Pro view of a project and the PWA
Project views are showing different things. Basically, the PWA Project view
shows old information of that project. We tried republishing All Information
and republishing (Selected) Assignments. Both did not solve the problem.
Does anyone know how this could have happened or, more importantly, how to
fix this?

BTW, The users see the most up to date schedule (as seen in Proj. Pro).

Thanks for any help,
Mike
 
D

Deena Blazek

Have your administrator validate the OLAP built successfully, recently. (We
build ours nightly; however, depending on how large your organization is,
yours might be getting built weekly. The OLAP cube is what updates the data
viewed in PWA, decending to Portfolio Analyzer, etc.
 