bauer172uw
We have a situation where our Project Pro view of a project and the PWA
Project views are showing different things. Basically, the PWA Project view
shows old information of that project. We tried republishing All Information
and republishing (Selected) Assignments. Both did not solve the problem.
Does anyone know how this could have happened or, more importantly, how to
fix this?
BTW, The users see the most up to date schedule (as seen in Proj. Pro).
Thanks for any help,
Mike