G
GLT
Hi,
I have inherited a project that was a huge list of tasks.
I broke the project up into chunks and restructured the list tasks.
The problem with this project is that over the past year, staff has been
doing bits of the project and also other non project work.
When I look at the project plan now, it currently reports it as 51% complete.
From my own analysis, I think it around 80% complete.
The problem is this:
The project is reporting durations 310 days (in one section, 308 days in
another section, 156.75 days in another).
I understand that duration is a factor for a project finish date, but at
this stage I am not interested in including the duration as part of the %
complete.
I only would like to see how much work has been done, and how much work is
left to complete (i.e. I do not want duration to be a factor in the %
complete result).
Can anyone advise how I would achieve this?
Any help is greatly appreciated.
Cheers.
I have inherited a project that was a huge list of tasks.
I broke the project up into chunks and restructured the list tasks.
The problem with this project is that over the past year, staff has been
doing bits of the project and also other non project work.
When I look at the project plan now, it currently reports it as 51% complete.
From my own analysis, I think it around 80% complete.
The problem is this:
The project is reporting durations 310 days (in one section, 308 days in
another section, 156.75 days in another).
I understand that duration is a factor for a project finish date, but at
this stage I am not interested in including the duration as part of the %
complete.
I only would like to see how much work has been done, and how much work is
left to complete (i.e. I do not want duration to be a factor in the %
complete result).
Can anyone advise how I would achieve this?
Any help is greatly appreciated.
Cheers.