L
lyndad
I am setting up a project designing and developing training which has to run
alongside existing training commitments for the team. I wanted to use
individual resource calendars but was advised the company doesn't like these
used in projects. It has been suggested that the training commitments are
entered as a recurring task, however they vary from week to week - one week
it can be four days split between four trainers, the next three days split
between three trainers. Can anyone advise the best way of entering the
existing commitments?
alongside existing training commitments for the team. I wanted to use
individual resource calendars but was advised the company doesn't like these
used in projects. It has been suggested that the training commitments are
entered as a recurring task, however they vary from week to week - one week
it can be four days split between four trainers, the next three days split
between three trainers. Can anyone advise the best way of entering the
existing commitments?