J
JaneH
I am working in Project 2000 and enter all durations as hours as we calculate
all task as man hours. In the summary task if we have all tasks in that
phase starting one after another with finish to start links we can see the
number of man hours needed for that part of the project in the duration
column. However if the project is not that helpful (as is usual) the number
of hours is an elapsed duration (the number of hours between start and
finish). Is there a way that I can have the total number of hours needed for
each phase displayed? In the summary task would be good but not absolutly
necessary if there is another way.
Thanks in advance.
all task as man hours. In the summary task if we have all tasks in that
phase starting one after another with finish to start links we can see the
number of man hours needed for that part of the project in the duration
column. However if the project is not that helpful (as is usual) the number
of hours is an elapsed duration (the number of hours between start and
finish). Is there a way that I can have the total number of hours needed for
each phase displayed? In the summary task would be good but not absolutly
necessary if there is another way.
Thanks in advance.