Hi,
We created a Master Project in PS2007 and inserted sub-projects in it as
read-only.
But when we publish the Master Project it also publishes assignments updates
of the sub-projects although these projects are read-only.
We would like to avoid it.
I was thinking of breaking the Link and Publishing it and re-establish the
link after publishing the master.
Any thoughts ?
We created a Master Project in PS2007 and inserted sub-projects in it as
read-only.
But when we publish the Master Project it also publishes assignments updates
of the sub-projects although these projects are read-only.
We would like to avoid it.
I was thinking of breaking the Link and Publishing it and re-establish the
link after publishing the master.