[Q]: How to change default period in VIEW TASK

N

Neil Greene

When logging into Project Web, and going to "View my tasks", I would like the
default date range in this view, to be modified from its default (or current
setting) of 2 week period starting on Sunday, to a different period
definition (maybe by 1 week, or starting on Monday)

How can I change my current setting?
 
D

Dale Howard [MVP]

Neil --

If you are talking about how to change this for everone in the organization,
then do the following:

1. Log into PWA with administrator permissions
2. Click Admin - Customize Project Web Access
3. In the Time Period Settings section, set the Week starts on value to
Monday, and the Number of weeks spanned value to 1
4. Click the Save Changes button

Hope this helps.
 