J
Jim Whiteford
In the resource names column I am receiving brackets with a number like
[1.64]. I have my resource pool set up for groups like Wiring team with max
units of 4. My question is regarding the 1.64. Is this number of resources of
the 4 needed to complete the amount of work over the duration indicated or is
this telling me that I need 1.64 more people to complete the amount of work
in the duration allotted?
Mike G. replied
Try Window/Split, click on an appropriate task, and in the bottom pane you
will see the number of Units of a resource that have been assigned. This is
the number you see in the [].
Hope this helps.
I looked as indicated and see the units are showing 1.64. I don't understand
why it is showing 1.64 when I have set up the resource pool with units to be
4. When first created the task type was set as "fixed duration" since I am
using a template for steps and duration. I then updated the work....
Is this why the units are showing 1.64 because when I typed in the work
hours it modified the resources to complete the number of hours in the set
duration? If so, to prevent this in the future should I pull in the template
and change the task type to fixed units prior to inputting the work hours?
[1.64]. I have my resource pool set up for groups like Wiring team with max
units of 4. My question is regarding the 1.64. Is this number of resources of
the 4 needed to complete the amount of work over the duration indicated or is
this telling me that I need 1.64 more people to complete the amount of work
in the duration allotted?
Mike G. replied
Try Window/Split, click on an appropriate task, and in the bottom pane you
will see the number of Units of a resource that have been assigned. This is
the number you see in the [].
Hope this helps.
I looked as indicated and see the units are showing 1.64. I don't understand
why it is showing 1.64 when I have set up the resource pool with units to be
4. When first created the task type was set as "fixed duration" since I am
using a template for steps and duration. I then updated the work....
Is this why the units are showing 1.64 because when I typed in the work
hours it modified the resources to complete the number of hours in the set
duration? If so, to prevent this in the future should I pull in the template
and change the task type to fixed units prior to inputting the work hours?