Question from fantasy land

B

Bryan A

Just for the sake of argument lets say someone finishes a task early. HA!!
I know, but it could happen.

Let's say I save a baseline work to 50 hrs and my resources completes it in
40hrs. How do I enter Actual Work to 40hrs and the % Work Complete to 100%
all at the same time?

Thanks for you help,
Bryan
 
J

Jan De Messemaeker

Hi Bryan,

Make sure to insert a column Remaining Work
Enter Actual Work 40 and Remaoining Work 0
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
B

Bryan A

Hey that worked!! Now if anyone ever finishes a task early I'll know what
to do. Thanks!

Bryan
 