S
Shahriar Nour Khondokar
This is probably more about project management in general, then MS Project
specific. But somebody please help me here or atleast guide me to a
place/resource where i can find the answers...
....
Here is the problem:
Lets say I got a project consisting of 5 tasks with estimated work and
status as shown below:
T1 - 5hrs - 100% complete - Actual work logged is 5hrs
T2 - 10hrs - 100% complete - Actual work logged is 10hrs
T3 - 10hrs
T4 - 20hrs
T5 - 5hrs - 100% complete - Actual work logged is 5hrs
So, percentage work complete is: 20/50 * 100 = 40%
Now lets think of a slightly different scenario:
We still got the 5 tasks above but with different Actual values:
T1 - 5hrs - 100% complete - Actual work logged is 10hrs
T2 - 10hrs - 100% complete - Actual work logged is 20hrs
T3 - 10hrs
T4 - 20hrs
T5 - 5hrs - 100% complete - Actual work logged is 10hrs
WHAT I badly NEED
is a mathematical formula that can be used to calculate percentage work
completion in such scenarios.
Somebody please, please help me. I would have posted it somewhere else if i
knew of any other place where as knowledgeable responses are received as
promptly as they are here.
Thank you.
specific. But somebody please help me here or atleast guide me to a
place/resource where i can find the answers...
....
Here is the problem:
Lets say I got a project consisting of 5 tasks with estimated work and
status as shown below:
T1 - 5hrs - 100% complete - Actual work logged is 5hrs
T2 - 10hrs - 100% complete - Actual work logged is 10hrs
T3 - 10hrs
T4 - 20hrs
T5 - 5hrs - 100% complete - Actual work logged is 5hrs
So, percentage work complete is: 20/50 * 100 = 40%
Now lets think of a slightly different scenario:
We still got the 5 tasks above but with different Actual values:
T1 - 5hrs - 100% complete - Actual work logged is 10hrs
T2 - 10hrs - 100% complete - Actual work logged is 20hrs
T3 - 10hrs
T4 - 20hrs
T5 - 5hrs - 100% complete - Actual work logged is 10hrs
WHAT I badly NEED
is a mathematical formula that can be used to calculate percentage work
completion in such scenarios.
Somebody please, please help me. I would have posted it somewhere else if i
knew of any other place where as knowledgeable responses are received as
promptly as they are here.
Thank you.