B
brent
I am using Project 2007 to manage a small (<100 lines), very basic, rolling
manufacturing production schedule. Without notice, the tasks in the file
become scrambled when the file is re-opened after saving edits. The schedule
is edited and re-saved several times a weeks by a single user. - possible
fragementation issue - however all the posted 'fixes' for this have not
worked.
I am using only the basic functionality of the software - linked tasks and
resource filtering (very basic!). Is this a common 'bug' with MSP? I have
used MSP for years without issue, but only recently started using 2007. Any
ideas would be appreciated!
manufacturing production schedule. Without notice, the tasks in the file
become scrambled when the file is re-opened after saving edits. The schedule
is edited and re-saved several times a weeks by a single user. - possible
fragementation issue - however all the posted 'fixes' for this have not
worked.
I am using only the basic functionality of the software - linked tasks and
resource filtering (very basic!). Is this a common 'bug' with MSP? I have
used MSP for years without issue, but only recently started using 2007. Any
ideas would be appreciated!