K
kevin w
Hi all
Project 2000
Is it possible to add a number field and put in, say, the total number of
units, and assign a resource to produce those units, but have MS Project
monitor that the maximum possible rate of producing said units is not
exceeded for that resource?
I know what I want to acheive, but I'm not familiar with how it can be done
with automatically.
Say 'Crew A' can produce 100units per week, I have 1000 units total to be
produced at different parts of my site, some sets of units are larger than
others. I have to give to Crew A enough work to have them fully occupied.
Can I input the size of the set of units somewhere and the production rate
for Crew A and let Project tell me where I have problems?
Or
Must I work durations based on the size of the set of units and let Crew A
be fully occupied on each task?
I hope I've explained it well enough.
I'm guessing that there's a place to enter the rate of production for a
resource, and a place to say how much of the output is to be produced, and
Project will tell me if my Crew cannot meet the tasks being assigned to it.
Thanks in advance
/kw
Project 2000
Is it possible to add a number field and put in, say, the total number of
units, and assign a resource to produce those units, but have MS Project
monitor that the maximum possible rate of producing said units is not
exceeded for that resource?
I know what I want to acheive, but I'm not familiar with how it can be done
with automatically.
Say 'Crew A' can produce 100units per week, I have 1000 units total to be
produced at different parts of my site, some sets of units are larger than
others. I have to give to Crew A enough work to have them fully occupied.
Can I input the size of the set of units somewhere and the production rate
for Crew A and let Project tell me where I have problems?
Or
Must I work durations based on the size of the set of units and let Crew A
be fully occupied on each task?
I hope I've explained it well enough.
I'm guessing that there's a place to enter the rate of production for a
resource, and a place to say how much of the output is to be produced, and
Project will tell me if my Crew cannot meet the tasks being assigned to it.
Thanks in advance
/kw