Yes.
Take one of the projects.
Go to the insert menu, select project
In the dialog box that comes up select the project AND make sure that the
"Link to Project" box is NOT checked.
This will insert all the activities from the second project into the first
one (just like a cut and paste)
-Jack
Take one of the projects.
Go to the insert menu, select project
In the dialog box that comes up select the project AND make sure that the
"Link to Project" box is NOT checked.
This will insert all the activities from the second project into the first
one (just like a cut and paste)