L
LisaD
We are using PWA 2007.
I re-assigned a task from the My Tasks page to another resource (using the
Reassign Work button) , then approved the change to push it to the project
plan.
Then I checked the project plan, and the task now has both resources names.
It did not replace one resource with the other, it appended the new resource
name.
I could swear that I tested this before and it worked fine.
Any explanation?
Thanks
I re-assigned a task from the My Tasks page to another resource (using the
Reassign Work button) , then approved the change to push it to the project
plan.
Then I checked the project plan, and the task now has both resources names.
It did not replace one resource with the other, it appended the new resource
name.
I could swear that I tested this before and it worked fine.
Any explanation?
Thanks