We are trying to see if we can use Resource Manager to reassign tasks
assigned to generic resource to a named resource. I know how to Reassign
task from My Work section. however, the problem is seeing task assigned to
generic resource.
I have defined a basic RBS with two generic resources under a Resource
Manager. I then built an Enterprise Team using a few named resources and the
two generic resources under the Resource Manager. I then assigned generic
resources to tasks. Idea is that Resource Manager will then substitute
generic resources with named resources.
However, when I log into PWA using Resource Manager I do not see the task
assigned to generic resources. Is there any way to see this tasks from PWA
and then re-assign them to named resources besides having PM do it?
assigned to generic resource to a named resource. I know how to Reassign
task from My Work section. however, the problem is seeing task assigned to
generic resource.
I have defined a basic RBS with two generic resources under a Resource
Manager. I then built an Enterprise Team using a few named resources and the
two generic resources under the Resource Manager. I then assigned generic
resources to tasks. Idea is that Resource Manager will then substitute
generic resources with named resources.
However, when I log into PWA using Resource Manager I do not see the task
assigned to generic resources. Is there any way to see this tasks from PWA
and then re-assign them to named resources besides having PM do it?