I have 5 employees who need to be in a recurring task (meeting).
I need all of them to be as resources for the task.
What is the best way to do this?
Shouldn't it look like this?
Meeting
Meeting 1 2Hours 0.25days
EmpA(25%),EmpB(25%),EmpC(25%),EmpD(25%),EmpE(25%)
Meeting 2 2Hours 0.25days
EmpA(25%),EmpB(25%),EmpC(25%),EmpD(25%),EmpE(25%)
Meeting 3 2Hours 0.25days
EmpA(25%),EmpB(25%),EmpC(25%),EmpD(25%),EmpE(25%)
So EmpA actually worked 25% of his time for Meeting 1 AND
the meeting lasted 2 hours which is equivalent to 0.25days. Right?
I can't seem to get it to look like this in Project. Am I heading
the right direction? Thank You.
I need all of them to be as resources for the task.
What is the best way to do this?
Shouldn't it look like this?
Meeting
Meeting 1 2Hours 0.25days
EmpA(25%),EmpB(25%),EmpC(25%),EmpD(25%),EmpE(25%)
Meeting 2 2Hours 0.25days
EmpA(25%),EmpB(25%),EmpC(25%),EmpD(25%),EmpE(25%)
Meeting 3 2Hours 0.25days
EmpA(25%),EmpB(25%),EmpC(25%),EmpD(25%),EmpE(25%)
So EmpA actually worked 25% of his time for Meeting 1 AND
the meeting lasted 2 hours which is equivalent to 0.25days. Right?
I can't seem to get it to look like this in Project. Am I heading
the right direction? Thank You.