J
JimS
Hi,
In my macro I need to update a task so that the end date matches one stored
in a variable. I presume that the correct way to do this is to set the
duration of the task so that the end date matches. But, if a task has
started, I need to set the remaining duration. If I'm going to calculate the
remaining duration, I need to know what date it was effective (so rem
duration = target end date - effective date for rem duration). Is there such
a date that I can use - is it the status date or is there something task
specific?
Or is there a better way of updating the task so that it finishes on a
specific date?
Cheers
JimS
In my macro I need to update a task so that the end date matches one stored
in a variable. I presume that the correct way to do this is to set the
duration of the task so that the end date matches. But, if a task has
started, I need to set the remaining duration. If I'm going to calculate the
remaining duration, I need to know what date it was effective (so rem
duration = target end date - effective date for rem duration). Is there such
a date that I can use - is it the status date or is there something task
specific?
Or is there a better way of updating the task so that it finishes on a
specific date?
Cheers
JimS