I have an in progress task and I'm entering updates on a daily bases (via
View / Task Usage).
Two questions:
1) what is the status date and how does it relate to how I am entering data?
2) how can I add time remaining to a task without project rescheduling
everything? Ie, I don't care about resource overallocations due to added
required work.