Remaining Work in Resource Usage view

T

TP

Hello,
In the Resource Usage view, I have added the Remaining Work column.
Unfortunately, this column shows actuals work instead of Remaining work for
projects that are not opened. So Project managers can not rely on remaining
work showed for a reousrce unless having the right access to open all its
projects.

What is the most userfriendly way to check Remaining work of a resource,
working on several projects, for several Project managers?

Thanks
 
M

Mike Glen

Hi TP,

Which version f Project are you using? If a server is in use, try posting
on the server newsgroup. Please see FAQ Item: 24. Project Newsgroups.
FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
G

Gérard Ducouret

TP,

In PWA, have you tried the View Resource Assignments page ?

Gérard Ducouret
 
T

TP

Hi Gérard
Finallly, I have created a cube view. It's a workaround not fully
userfriendly because we build our cube only every week.
The issue with the Assignment view is that a PM can not see all assignments
if a resource works for other PM.
Moreover, I have noticed again something weird: with my userid (admin
right), I do not see Admin projects in the Assignment view. But with a PM
userid, in the same view, Admin projects are shown.
 