PriKobo

I would like to see the remaining work (Man hour) at the resource usage view
by month. Has anyone the solution to this problem?
Many thanks
 
G

Gérard Ducouret

ProiKobo,

Set the timescale unit of your Resource Usage view to Months.
Insert the Work and the Actual Work rows if they are not displayed (Right
Click on a yellow cell)
The remaining Work in this view is the Work (scheduled) without any Actual
Work in front of it.