Remove overallocation before today

E

Espen

Resources that is used in my project is sometimes overallocated, and this is
shown by turning the resource red, this is fine. But when the date that the
resource is overallocated is passed, I want the resource to go back to black,
is this possible? I only want the overallocation to work from today and
forward.

thanks for any help
Espen
 
J

Jan De Messemaeker

Hi,

That happens when you do the logical thing, i.e. setting the work before
today as "done" or "actual".
Toiols, Tracking, update project, first radio button.
HTH
 
E

Espen

Thank you!

That worked fine, but the update of project dont seem to be continuous, are
there any ways to make this happend without updating every project every day?
I juse MS Project 2000.
 
J

Jan De Messemaeker

Hi Espen,

Sorry, No. The idea is that you first adjust tasks manually before setting
everything to 100%..
 