Hi Dan,
These results may be correct if you changed, for example, the task duration
while the task type was set to "fixed work" (while the %Complete was already
50% for ex). The resource Jim L is assigned full time during some days and
part time the other days.
When you *replace* Jim L by Dan, Ms Project replace Jim L only on the
remaining work, may be at part time.
So after the replacement, the assignments are : Jim L [100%];Dan [50%]
Hope this helps,
Gérard Ducouret
"Dan McCarty" <
[email protected]> a écrit dans le message de
Gérard Ducouret said:
As said previously, don't *delete* the resource, *replace* it (Click the
"Replace" button)
I *did* try to replace it. When I click the Replace button the
resource list goes from
Jim L [100%]
to
Dan [50%]
Jim L [100%]
If I try to click his name and Replace him *again* (with myself again),
I get a message about not being able to assign a resource to a task
twice. That makes sence.
But when I click OK to dismiss the message another message pops up
about deleting an item with "actual values" (as opposed to just
"values," apparently).
I don't want to delete any work done on the project. How can I just
replace the remaining work with another resource?
This is Project 2003, BTW.