How do I do a report that shows tasks that are ending by a given date in MS
Project?
 
J

John

Mach Mach said:
How do I do a report that shows tasks that are ending by a given date in MS
Project?

Mach Mach,
For starters you could try the "Should Start/Finish by" built-in filter.
You'll find it listed under Project/Filtered for/More filters.

John
Project MVP
 