Hi Justin,
You are welcome and thanks for the feedback.
About your second question -- not dumb at all -- just bear in mind, Project
doesn't assign resources, you do.
That being said, a couple of things to keep in mind:
Resource leveling only works when a resource is assigned to multiple tasks
that overlap in time and the sum of their resource assignments (Peak Units)
is greater than their maximum units. Project will *not* change work
assignment units. So you can create a situation where the resource is not
most "productive". For example, if a resource's maximum units are 100%
(default) and I assign the resource at 60% to two tasks occurring at the
same time, the resource is overallocated because their peak units (120%) is
greater than their max. units (100%). If I level, project will delay the
second task until the end of first one, leaving the resource assigned at 60%
to each task. Not truly "productive", it just resolves the overallocation.
Hope this helps. Let us know how you get along.
Julie
WhyIsEverythingSoConfusing said:
Whoa. Cool. Thanks! It works wonderfully.
I'm still a novice with this, so this might sound dumb, but ... As a
general
rule, will Project assign all resources the same way until Leveling is
used?
And is leveling simply the process of trying to be as efficient as
possible,
or said another way, getting productive work out of every resource over
{insert leveling timeframe here}?
--------------
Justin
JulieS said:
Hi Justin,
Yes, insert the field [Level Assignments] and you can control on a task
by
task basis whether project can adjust individual assignments on a task.
Hope this helps. Let us know how you get along.
Julie
WhyIsEverythingSoConfusing said:
For some of my tasks I'd like to require that the resources work during
the
same times (for example, they all need to be present for a meeting). I
guess
it is also important not only that Project schedule all resources for
the
same number of hours, but also that is schedule them for the SAME hours
(like
1-5 pm).
I can accomplish this overall (I think), by unchecking the "Leveling
can
adjust individual assignments on a task" checkbox within Resource
Leveling.
I want to be able to choose this on a task-by-task basis. Is this
possible?