Brian Michalk
I am jumping into the middle of an existing team and am setting up some
metrics to get a feel for how much each person is assigned and so forth.
I have entered all the resources and tasks and sort of used a person
(resource) as the criteria for linking the tasks according to the task
priority. From there I want Project to schedule out into the future how long
it will take a person to complete his tasks.
I would like Project to look at the % complete, and move that task to before
today, and reschedule the resources remaining tasks.
It looks like I could either use "status date", or
tools->tracking->update_projects for this. Is this the best way to do this?
metrics to get a feel for how much each person is assigned and so forth.
I have entered all the resources and tasks and sort of used a person
(resource) as the criteria for linking the tasks according to the task
priority. From there I want Project to schedule out into the future how long
it will take a person to complete his tasks.
I would like Project to look at the % complete, and move that task to before
today, and reschedule the resources remaining tasks.
It looks like I could either use "status date", or
tools->tracking->update_projects for this. Is this the best way to do this?