Joaquim Amado Lopes
Greetings.
I'm developing a prototype for the production planning of a small
factory. We've decided for a master project with a number of
subprojects (one for each order). The resource pool is on the master
project.
Every day, the planner needs to update the completed tasks and
reschedulle those that didn't start when they should have.
Tried to reschedulle, in the master project, for all the subprojects
but it didn't work. I need to open each of the subprojects and
reschedulle one by one.
As each subproject is relatively short (a couple of days) and it may
add up to 100 simultaneous sub-projects, reschedulling one by one will
consume too much time to be practical.
Is there any way to reschedulle the uncompleted work for all the
subprojects, no matter how many they are, with only a few steps?
Thank you for your help,
Joaquim Amado Lopes
I'm developing a prototype for the production planning of a small
factory. We've decided for a master project with a number of
subprojects (one for each order). The resource pool is on the master
project.
Every day, the planner needs to update the completed tasks and
reschedulle those that didn't start when they should have.
Tried to reschedulle, in the master project, for all the subprojects
but it didn't work. I need to open each of the subprojects and
reschedulle one by one.
As each subproject is relatively short (a couple of days) and it may
add up to 100 simultaneous sub-projects, reschedulling one by one will
consume too much time to be practical.
Is there any way to reschedulle the uncompleted work for all the
subprojects, no matter how many they are, with only a few steps?
Thank you for your help,
Joaquim Amado Lopes