Rescheduling uncompleted work

  • Thread starter Joaquim Amado Lopes
  • Start date
J

Joaquim Amado Lopes

Greetings.

I'm developing a prototype for the production planning of a small
factory. We've decided for a master project with a number of
subprojects (one for each order). The resource pool is on the master
project.

Every day, the planner needs to update the completed tasks and
reschedulle those that didn't start when they should have.
Tried to reschedulle, in the master project, for all the subprojects
but it didn't work. I need to open each of the subprojects and
reschedulle one by one.

As each subproject is relatively short (a couple of days) and it may
add up to 100 simultaneous sub-projects, reschedulling one by one will
consume too much time to be practical.

Is there any way to reschedulle the uncompleted work for all the
subprojects, no matter how many they are, with only a few steps?

Thank you for your help,
Joaquim Amado Lopes
 
J

Jan De Messemaeker

Hi,

Show all subtaks in the master, select all, Tools, Tracking, update project,
reschedule uncompleted... FOR SELECTED TASKS

HTH
 
J

Joaquim Amado Lopes

Thank you, Jan.

(My newsreader didn't receive your post and I only saw it today in
Google)

This is one of those big problems with an incredible simple solution.
:-]

Take care,
Joaquim Amado Lopes
 