Rescheduling unstarted tasks to today's date

M

Morten

Hi,

I would like to reschedule unstarted tasks, as if they were entered today.

I have some tasks that have a planned start date earlier than todays date.
These tasks have not started yet, and I would like to reschedule them, as if
they were deleted and reentered.

I know I can set the option: Move start of remaining parts before status
date forward to status date. But this only applies to tasks that have been
started, but not completed.

Regards,

Morten Frederiksen
 
G

Gérard Ducouret

Hello Morten,
Select these late tasks, then:
Tools / Tracking / Update Project / Reschedule uncompleted work to start
after...
Selected Tasks
OK

Gérard Ducouret
 
M

Morten

Thanks Gérard,

but, it seems to me, that this doesn't reschedule tasks that have not yet
started...

I managed to get the functionality I wanted by changing all dates, between
Project-Start-Date and today, to non-working days.

This way Project reschedules all tasks, including the not-started.

Is this the only way to get this functionality?

regards,

Morten
 
G

Gérard Ducouret

Morten,
No ! Try again, there is something wrong in your process ! this feature
works fine (I used it hundred of times)
Take care of the date after the option : Reschedule uncompleted work to
start after:.....

Tell me if it works now,

Gérard
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top