Hi,
I would like to reschedule unstarted tasks, as if they were entered today.
I have some tasks that have a planned start date earlier than todays date.
These tasks have not started yet, and I would like to reschedule them, as if
they were deleted and reentered.
I know I can set the option: Move start of remaining parts before status
date forward to status date. But this only applies to tasks that have been
started, but not completed.
Regards,
Morten Frederiksen