R
Rich
I have a task that takes 40 hours to complete. I asssign 3 people to
it. Two work full time and 1 works part time. If I set the resource
allocation for 100% for all users project takes the 40 hours and gives
each person 13.33 hours of work to do causing the task to take longer
then needed as the part time user takes more days to complete is 40
hours.
I would like to be able to
1. Have it allocate the resources based on getting the task done in
the last amount of calandar days rather then giving each person the
same amount of work
2. I have a special employee that could be put to better use on
another task and a basic working that is just qualified for this task.
I would also like to shift the resources so that it uses my basic
worker full time on a basic task and only uses my speciality worker if
he is not needed for another task.
Are either or both of these time allocation methods possible in
microsoft project? I tried resource leveling which I thought worked
once but didnt have any luck after the first time I had it level the
project. The speciality employee also charges more per hour if that
can help microsoft project to figure out resource allocation.
it. Two work full time and 1 works part time. If I set the resource
allocation for 100% for all users project takes the 40 hours and gives
each person 13.33 hours of work to do causing the task to take longer
then needed as the part time user takes more days to complete is 40
hours.
I would like to be able to
1. Have it allocate the resources based on getting the task done in
the last amount of calandar days rather then giving each person the
same amount of work
2. I have a special employee that could be put to better use on
another task and a basic working that is just qualified for this task.
I would also like to shift the resources so that it uses my basic
worker full time on a basic task and only uses my speciality worker if
he is not needed for another task.
Are either or both of these time allocation methods possible in
microsoft project? I tried resource leveling which I thought worked
once but didnt have any luck after the first time I had it level the
project. The speciality employee also charges more per hour if that
can help microsoft project to figure out resource allocation.