Marcus Pierce
How can I make so that, if a resources allocation is 40% max per day (3 hrs),
and I assign a task that is 4 hours long, Project will assign three hours one
day and 1 hour the next day without overallocating the resource. Can I do
this retroactively?
--Marcus