M
material bob
Can project keep track of inventory issues? A very basic example:
Assume I have a stock of 100 steel pillars. A project requires 50 of these
pillars for
a certain task on the first of januari. Another task is the removal of these
pillars. This task is to be completed on the first of april, from this date
on these pillars should be added to my stock, totalling it to 100 pieces
again. Can this automatically be done? Because the next project which starts
on the fifth of april requires 60 pillars....
In other words: can project keep an active track of my resources? And if the
first project is delayed by a month, will I get a message telling me the next
project has too little resources?
Assume I have a stock of 100 steel pillars. A project requires 50 of these
pillars for
a certain task on the first of januari. Another task is the removal of these
pillars. This task is to be completed on the first of april, from this date
on these pillars should be added to my stock, totalling it to 100 pieces
again. Can this automatically be done? Because the next project which starts
on the fifth of april requires 60 pillars....
In other words: can project keep an active track of my resources? And if the
first project is delayed by a month, will I get a message telling me the next
project has too little resources?