J
Jim Aksel
Good morning peers. Using Project2003.
Project Manager has assigned a group of people to work a project- Resource A
is available 50%, Resource B is available 25%, etc. They will divide
themselves among "n" simultaneous tasks and get done what they can. The
total amount of allowed work is given by the period of performance and the
%units. We should assume these are Level of Effort tasks.
If 4 tasks are in play today, then resouce A will work 1 hour on each task,
resource B will work 0.5 hrs. Task start/finishes are different for each
task in play.
A large group of tasks is assigned and every one of them will have the same
resource assignments -- A and B. I have "n" tasks. I would like to be able
to select all these tasks and tell project: "Assign A and B to all these
tasks such that they are not overloaded while keeping all the same dates." I
can make the tasks fixed duration, etc. That is, I want Project to determine
the correct units% day by day so A & B are not overloaded.
So on any given day, I will have "n" tasks in play. The total allocation
of A is not to exceed 50% of their time (4 hours among "n" tasks) and B is
25% (2 hours) among the same "n" tasks. "Tomorrow", "n" becomes a new number
"m" because there are a new set of tasks in play (most of which are the same
as yesterday). Now I want to divide up A and B using the same rules. The
task durations are typically 5 days to 3 weeks (variable) and I need to load
the resources so that are not overloaded on any given day.
After making these assignments, I will need to return to the PM to verify
staffing plan and if there is a sufficeint amount of hours assigned to each
task to allow the work to be done. If not, he will either need more people
or more duration which is going to be a customer driven decision.
Am I asking it to do too much? Should I be putting on my VBA hat and
attacking it that way, or hasn't my Starbucks coffee kicked in yet this
morning?
Project Manager has assigned a group of people to work a project- Resource A
is available 50%, Resource B is available 25%, etc. They will divide
themselves among "n" simultaneous tasks and get done what they can. The
total amount of allowed work is given by the period of performance and the
%units. We should assume these are Level of Effort tasks.
If 4 tasks are in play today, then resouce A will work 1 hour on each task,
resource B will work 0.5 hrs. Task start/finishes are different for each
task in play.
A large group of tasks is assigned and every one of them will have the same
resource assignments -- A and B. I have "n" tasks. I would like to be able
to select all these tasks and tell project: "Assign A and B to all these
tasks such that they are not overloaded while keeping all the same dates." I
can make the tasks fixed duration, etc. That is, I want Project to determine
the correct units% day by day so A & B are not overloaded.
So on any given day, I will have "n" tasks in play. The total allocation
of A is not to exceed 50% of their time (4 hours among "n" tasks) and B is
25% (2 hours) among the same "n" tasks. "Tomorrow", "n" becomes a new number
"m" because there are a new set of tasks in play (most of which are the same
as yesterday). Now I want to divide up A and B using the same rules. The
task durations are typically 5 days to 3 weeks (variable) and I need to load
the resources so that are not overloaded on any given day.
After making these assignments, I will need to return to the PM to verify
staffing plan and if there is a sufficeint amount of hours assigned to each
task to allow the work to be done. If not, he will either need more people
or more duration which is going to be a customer driven decision.
Am I asking it to do too much? Should I be putting on my VBA hat and
attacking it that way, or hasn't my Starbucks coffee kicked in yet this
morning?